The installation of the iZone power monitoring current transducers (CT's) must be undertaken by an electrician in accordance with AS/NZ 3000:2007 Electrical installations

SETUP THE CMPD

3️⃣ At the same time press the Pair button on the touchscreen or the App

4️⃣ The blue LED will flash rapidly to indicate this device is paring to the system

5️⃣ The screen will confirm that this device is configured and its allocated Device number

6️⃣ Replace the back cover

FIT THE CT SENSOR CLAMPS

1️⃣ You need to ensure the CT sensor clamps are installed on the correct cable to receive the correct readings

These options are a guide only and you should consult your electrician to ensure the location of the CT sensors is correct

It may be necessary for the electrician to modify the wiring in your switchboard to achieve the correct result for your particular installation

2️⃣ Pull the clip on the CT clamp and open it

3️⃣ Place the cable in the CT and close it. Make sure the clip on the CT clicks closed and locks in place

4️⃣ Drill a hole in the side or bottom of the switchboard. It should be large enough to accommodate all the CT cables you are installing plus a rubber grommet

5️⃣ Install a suitable rubber grommet into the hole (Not supplied)

6️⃣ Pass the connectors through the hole

7️⃣ If the switchboard is located outdoors, ensure the penetration into the switchboard is waterproof

SINGLE PHASE INSTALLATION WITH SOLAR

THREE PHASE INSTALLATION WITH SOLAR

SINGLE PHASE INSTALLATION MONITORING TOTAL POWER USED, AIRCON AND LIGHTING

TWO PHASE INSTALLATION MONITORING TOTAL POWER USED AND AIRCON