C210: System Series - Installation Guide

PAGE CONTENTS

 

ONLINE INSTALLATION WIZARD

image-20240213-020431.png

 

C210 KIT CONTENTS

1x C155: CPU

1x CT24ACM: 24v Power Supply

1x CFC12S: 12m Cat5e Cable

1x CLCSW: Nite Wall Controller

1x C325#: AC Unit Interface (Brand Specific)

1x COCB: Smart Hub (Optional Extra)

1x CR: Repeater (Optional Extra)

 

 

The C155 and C325# can be installed close to the indoor fan coil unit

If any wireless bridge (COCB) is not within the range of the C155 then additional repeaters (CR) should be added to help relay the signal from the field device to the C155 and the bridge

Do not run the cat5e cables alongside 240 Volt wiring

When installing network cables down wall cavities or chasing network cables into walls, tape up and protect the RJ45 connector to avoid damage to the connectors

Always install zones in consecutive ports starting at Zone number one (1)

The C155 is marked with the zone port numbers

Do not directly hard wire the CT24ACM into the AC unit’s power supply

Connect Zone Damper Actuators (CZDA) to the zone ports using the RJ12 cables as shown in the Wiring layout diagrams

Connect the Nite wall controller (CLCSW) to the iZone Net port using the RJ45 cables

Connect the AC unit control cable to the C155 / C325.

See AC unit wiring connection section for details - C325#: AC Unit Interface - Install Guides

The building must be fitted with a compatible Wi-Fi modem

For a list of approved and recommended modems - COCB - Smart Hub - Install Guide

If connecting the iZone system to a Home Automation system use the Ethernet connection on the bridge - iZone API Integration - Install Guide

Only connect the power supply to the CT24ACM port after all components have been connected

Any existing or new air conditioning units that require modification or additional boards to facilitate the correct operation of the iZone system, is the responsibility of the installing contractor

 

Nite Diagram.png