C210 KIT CONTENTS
1x C155: CPU
1x CT24ACM: 24v Power Supply
1x CFC12S: 12m Cat5e Cable
1x CLCSW: Nite Wall Controller
1x C325#: AC Unit Interface (Brand Specific)
1x COCB: Smart Hub (Optional Extra)
1x CR: Repeater (Optional Extra)
The C155 and C325# can be installed close to the indoor fan coil unit
If any wireless bridge (COCB) is not within the range of the C155 then additional repeaters (CR) should be added to help relay the signal from the field device to the C155 and the bridge
Do not run the cat5e cables alongside 240 Volt wiring
When installing network cables down wall cavities or chasing network cables into walls, tape up and protect the RJ45 connector to avoid damage to the connectors
Always install zones in consecutive ports starting at Zone number one (1)
The C155 is marked with the zone port numbers
Do not directly hard wire the CT24ACM into the AC unit’s power supply
Connect Zone Damper Actuators (CZDA) to the zone ports using the RJ12 cables as shown in the Wiring layout diagrams
Connect the Nite wall controller (CLCSW) to the iZone Net port using the RJ45 cables
Connect the AC unit control cable to the C155 / C325.
See AC unit wiring connection section for details - C325#: AC Unit Interface - Install Guides
The building must be fitted with a compatible Wi-Fi modem
For a list of approved and recommended modems - COCB - Smart Hub - Install Guide
If connecting the iZone system to a Home Automation system use the Ethernet connection on the bridge - iZone API Integration - Install Guide
Only connect the power supply to the CT24ACM port after all components have been connected